Europe · Evidence grade B

United Kingdom

The default estimate is $26 per million output tokens, ranking 36 of 45 countries for general inference in a 100 MW data center.

Scenario results

Default cost $26
Default rank #36
Difference from leader +16.6%
DeploymentWorkloadCostRank
100 MW data center General inference $26 36 of 45
100 MW data center Long context $59 38 of 45
100 MW data center Agentic engineering $133 39 of 45
On-prem solution General inference $35 42 of 45
On-prem solution Long context $79 42 of 45
On-prem solution Agentic engineering $180 43 of 45

All values are US dollars per million output tokens. Rankings are recalculated for every scenario.

How to read this estimate

Country-level inputs are screening proxies. Site selection requires hardware quotes, a utility connection study, a large-load tariff or PPA and a reproducible production benchmark.

Read methodology